00:01My name is Glenn Berger. I have approximately 20 years of experience managing GIS project as well…
00:10…projects as well as other IT types of projects in utilities, telco, government…
00:18…so I've done small projects, large projects, you name it.
00:23When I say 20 years, yeah, I started when I was 5, but, anyway…
00:32…so I've got some experience that I definitely want to share with you guys and Gerry, do you…
00:41I'm Gerry Clancy. I'm from our Washington, D.C., office, Glenn's former office…
00:47…and we together manage a wide variety of commercial, federal, state, and local projects…
00:54…that vary from very small, from a couple of days to a week to multimillion, multiyear-long engagements.
01:00So what we're going to try and talk about today is not all war stories, no client naming…
01:07…but to try and give you some guidance of what we've learned and…over the years.
01:14I've been with Esri…20 plus years. Let's just leave it at that.
01:19And most of that time in the Professional Services group managing projects from way back in the early ARC/INFO days…
01:26…and how we've migrated to the new patterns and so there's a lot of new things that if you're a project manager…
01:32…and have been growing up in project management, that are really changing underneath you…
01:36…so we really want to try and take this session to one of the key things about GIS and…
01:42…enterprise project management that are important and start that conversation with you.
01:46So that's what we're going to try and talk about.
01:50Want to go to the next slide.
01:54So, what…what Gerry and I have done in the past and we…we like to focus in on 10 key areas or 10 key focus areas…
02:03…that we think from a project management perspective, a project lead perspective…
02:09…areas that we want to share out based off of our years of experience.
02:17Some…some of those experiences are good. Some of them not so good.
02:22But…but sometimes those not-so-good experiences can teach you a lot more than the ones that go smooth and successful.
02:32So, we want to share those out.
02:35We do…we will share a few war stories. It's not all war stories, but we wanted to make sure that this…
02:43…shared with you in…in a…in as interactive a way as we can.
02:47So, as you have questions or if you want to share stories on…on your end or whatever, you don't have to wait to the end…
02:54…you can interrupt us.
02:56I will typically interrupt Gerry, and Gerry will typically interrupt me, and that's just the…
02:59Yes he will.
03:01That's just the way we are, so we want to make this as fun and engaging as we possibly can.
03:09You could see here, these are in no particular priority or…or rank order.
03:16All of them are important and there may be some on there that you're looking at right now and saying, well, what about this one?
03:21What about, you know, why is…why are these 10 and why is this other thing I've got fresh on my mind not on there.
03:29So please feel free to share that with us.
03:31This list does change slightly.
03:33We've changed it a couple times based off of feedback from the audience…
03:37…and maybe a particular experience that either Gerry or I are having on a project that we realize…
03:44…hey, this is something that we're seeing and we want to share it out.
03:50Even though they're not in any particular order of importance, for me…
03:57…this is…this is probably the one area that I really want to stress, at least from my perspective and as a new project leader…
04:05…or project manager that's entering down or beginning to enter into a project, is really critical to…
04:16…to understand what is the business workflow, what is the business opportunity that you're trying to solve.
04:22Why…why are you doing the project?
04:26As you're sitting there and you're thinking, you're looking at the slide right now…
04:29…if…if you're saying inside your mind that, well, hey, I'm doing the project to implement a GIS system.
04:36And that's not…that's not the right answer.
04:40That is the means. That's what you're going to do to deliver some business value to your organization.
04:46And you can't lose sight on that.
04:48Are you implementing a system to replace an existing legacy system that needs to be retired?
04:54Are you trying to drive efficiencies in a business process?
04:58Are you trying to improve productivity?
05:01There are a whole host of reasons why you as a project leader or project manager have been tasked with the project that…
05:09…that…that's been assigned to you that you're responsible for, and you can't lose sight of that.
05:16I don't know how many times I've been involved with a project and I personally, I think, we all kind of fall into this trap.
05:21You…you focus on project task.
05:24You're really focused on the project plan, you know…
05:27…maybe you're…you're…you're struggling around some particular functionality that's not, you know…
05:33…it was due yesterday and you find out, well, it's only 50 percent complete or whatever the case.
05:38And we have a tendency to really focus in that area, and we need to, obviously, I'm not saying you ignore that…
05:44…but I think it's…it's very important that you understand and…
05:48…focus as a laser beam on why are you actually doing the project for your organization.
05:59Fit the management of the project to its scale and scope.
06:02So, bottom line, all projects vary.
06:08They vary in complexity. They vary in duration. They vary in what they're actually trying to accomplish.
06:16And, to…to use the same project management approach or process for a project that is a week or two weeks in length…
06:27…or a month in length or something that's maybe two years in length can cause you some problems.
06:35Adapt your project management approach. Adapt how you want to manage a particular project to what that project demands.
06:44Now, when I'm saying that, I'm not…I'm not saying you're not focusing on the same constraints throughout…
06:50…that manage all projects or that are fundamental to all projects.
06:54Time, cost, and scope are all interdependent, you're balancing those against each other.
07:01All I'm saying is, if you find yourself with five project administrator-type people and one technical resource…
07:10…then you've probably got some things out of whack.
07:14You probably want to look at it from…what…what…keeping it simple but yet communicating the message and…
07:21…accomplishing the goals that…that you originally targeted to do.
07:25And a lot of that can be kind of reinforced by that first slide.
07:28You'll hear me reference this a lot and in…as I go through the slides, understanding the business value.
07:34Once again, understanding that and keeping that first and foremost as you go through execution of your project.
07:46Break it into small, workable pieces.
07:49I think a lot of us have, especially some of us who have been around for a while, have definitely embraced this concept.
07:58I think a lot of people are, you know, some of it is just…it's second nature to what we do.
08:05But, it can be kind of intimidating to have a two- or three-year project where you're trying to deliver brand new capabilities…
08:15…insert new technology into an organization, and breaking it up into smaller pieces, into different phases…
08:23…can certainly help you in that respect.
08:27It gives you an opportunity to under…to…to develop an understanding within…within the organization.
08:35It's important to remember that we're, in a lot of cases, we're delivering new technology, new functionality, new capabilities…
08:41…to an organization that maybe your stakeholders just aren't as familiar with.
08:48It gives you an opportunity to put the technology in front of them, put the solution in front of them…
08:53…let them understand what this really means when we say a GIS system.
09:00It allows you the opportunity to get buy-in as you go and to show success.
09:06You know, one that…that we've been or that I've been trying to drive is that initial phase could be something as simple as…
09:14…standing up the baseline technology, getting it in place, getting it installed.
09:20Maybe that could be the very first phase or the first spiral, first iteration, whatever you want to refer to it as…
09:26…where you put that in there, you stand it up, you really haven't started delivering business functionality yet…
09:32…or…or business workflows, but it gives an opportunity for those other users in the organizations…
09:37…to see exactly what you're talking about when you talk about GIS or geospatial functionality.
09:45I think this is really critical in today's technology environment.
09:49People are and end users are not going to wait for a year and a half to get a system up and running.
09:56They're just not.
09:57It's the…the technology will support small incremental bills and your end users are frantic to get things.
10:05So you really need to think, even in an enterprise, which is usually a very ugly, complex, integrated project.
10:13You really need to think about not the end goal of being 18 months or 2 years down the road.
10:19You need to break it up into three- and six-month project bills, and delivering things constantly to meet end goals.
10:26And, you know, the old project management method of waterfall or spend a year in requirements…
10:34…and then you're going to go to do some design, and then you're…
10:37…and three years later you still haven't got anything to show except a lovely set of documents.
10:42It's not going to fly.
10:44Really in this moving, fast world, your requirements are constantly changing…
10:50…and you really need to think about breaking your enterprise project up into small, manageable, deliverable-focused efforts.
10:58It's really critical at this stage.
11:01It's…and I guess the one thing that we encounter a lot is, we'll go in…
11:06…a project manager or a project lead will be familiar with our technology or they're…they understand GIS.
11:15Maybe it is in a GIS department within an organization.
11:19But obviously that's not all the time who the key stakeholder is on a particular project.
11:25It could be a dispatch group or a work order group or some other…
11:30…they're looking to a GIS group or a particular project lead to implement a system that provides a business function…
11:37…but they don't necessarily always understand what this is.
11:40A lot of people that maybe aren't involved in our industry are familiar with billing systems and customer information systems…
11:50…but they're not as familiar with geospatial technology.
11:53So using a phase-based approach allows you to come in, show some of the capability…
11:58…get them to understand exactly what the solution's about…
12:02…and you'll be surprised at how quick that can help you get that buy-in, start getting new ideas flowing, and it can go a long way.
12:12Are you going to Correct talk about Microsoft Project?
12:14Yeah. Yeah, the other thing is Microsoft Project, it's a wonderful tool…
12:20…obviously, or any…any project…project plan type of tool.
12:29Use this, you know, you as a project lead, I mean, you're a change agent, right?
12:33You're…you're the one that's bringing this system to the organization.
12:37Make sure to share it out and share what those major milestones are, what those tasks are…
12:42…even to people that may not be directly responsible or assigned within your project plan as resources.
12:48Remember, you know, you don't want to become the black box.
12:52You don't want to be that project that, hey, something's going on over there in the corner…
12:56…and, you know, hey, who knows when it's going to be done.
13:00Provide frequent updates.
13:02Now on the flipside of that is, be careful with the project plan.
13:07You know, by…by going at it from a multi…multiphase approach, you can put some detail on those first couple phases…
13:15…but you can go lighter in the…in the subsequent phases.
13:19If you're planning out task four, six, eight hours for…
13:24Don't do it. Yeah. Please, please don't do it.
13:26For project deliverables 24 months down the line, well guess what, I…I can tell you right away those are wrong.
13:33Those are going to change.
13:34Your dependencies are going to change.
13:36So, just kind of keep that in mind.
13:38You don't want to get to the point as a project leader, as a project manager…
13:42…where you're so heads-down in your project plan or your project schedule that you're missing the big picture.
13:50So there's a great little 20-minute workshop on the demo floor about building a project plan and good tools to use.
13:57It's on the little sheet that we handed out.
13:58We can certainly talk to you when that's going to be, but it's…don't get project planned to death.
14:04When we go into enterprise projects and we see a project plan that's this thick, I'll tell you right now…
14:09…the system's not going to work.
14:10I don't even have to look at the requirements.
14:12You…you can't manage at such a minutial level and be effective.
14:18So it's really, you know, the tools are there to be an efficient project, not to be a project in and of itself.
14:27So you really need to kind of make that balance work.
14:30Yeah, and, you know, I mean it's one thing when you're talking about delivering, you know, military-grade systems…
14:37…and those types of things or launching the space shuttle.
14:41And once again, we're…I just want to make sure this is clear.
14:44We're not saying you don't have a project schedule and you don't do project planning, you certainly do.
14:49But just do it to the right level.
14:51Don't get overwhelmed by that.
14:53That…that's not what you're really here for, not what you're being tasked to do.
14:58You're being tasked to get a project deployed to deliver capability.
15:02This is something that, as you notice, Gerry jumped up.
15:05I'm kind of rambling on about it, but this is important to us…
15:09…because both Gerry and I have a tendency to get pulled into some difficult situations or projects that are challenging…
15:17…or facing difficulty, and we both kind of swap war stories over time where it's…we both kind of go in and do…
15:25…right away we say, hey, let's see that project schedule, let's see your project plan.
15:30And if it makes a noise when it's put on the table, then we're very concerned, and we most of time understand what the problem is.
15:43You need to be in sell mode.
15:46Once again, this goes back to you being the change agent.
15:50Somebody has…has…has entrusted with you a…a project, an initiative that is going to potentially change, in some cases…
15:59…could drastically change an organization.
16:02It's going to deliver new capability that maybe somebody's never seen before.
16:08So, be in…be in that sell mode.
16:10Continue to emphasize what the project's about.
16:15Demonstrations of capability and functionality that the project has accomplished to your stakeholders, to the users…
16:24…is critical.
16:26Don't be afraid to sell what you've done.
16:29We have a tendency from a project standpoint to…to say, well, I've got a 24-month project duration…
16:39…and I've got, you know, 10 different phases that I'm scheduling.
16:43I'm…I get through maybe phase 1 and phase 2, and I don't see that as a significant accomplishment…
16:49…because I'm deep in the project and I'm like, hey, well I still have, you know, well over a year and a half to go before I'm done.
16:56But that…that can be a significant accomplishment, letting your stakeholders know that…that you're making progress…
17:04…getting them to buy in to what you're trying to do and what you're trying to accomplish…
17:10…and really most significantly getting that feedback.
17:14Are you on the right…are you heading in the right direction?
17:17Once again, when you communicate, when we talk about being in sell mode, what we mean is you're communicating…
17:23…you're saying, hey, you entrusted me to implement a project that was going to deliver X business value, improve productivity…
17:31…performance, whatever the case may be.
17:34When you status your stakeholders, when you status your customers, it should be in relation to that.
17:40It should be…it shouldn't be, hey, we just…we developed this workflow.
17:44I mean, that's important, but it's…we've developed this workflow…
17:48…and here's how it's addressing the capability that you've tasked me with implementing.
17:52And I think, you know, one of the things we tend to do as project managers, a really good thing is to, across all the spectrum…
18:00…look at single points of failure.
18:02So, all the geeks and bitheads who work on hardware, you're always talking about redundancy and replication.
18:09You need to be doing the same thing with your project sponsors.
18:12So the sell mode means that you need to be communicating and recruiting and getting people to buy into your enterprise vision…
18:21…because, you know, we've been in numerous situations where that project champion moves on four months into the project…
18:28…and all of a sudden you've got a vacuum and you've got no project champion…
18:33…and you just see this heading off a cliff.
18:35So, the whole idea behind this is visibility.
18:39It's often a difficult hat for project managers to where they want to be in a very logical, controlled environment…
18:45…and this is…this is spin and it is PR.
18:48But you are selling the…the value of the project, the benefits of the project, and you are…
18:56…you are spreading the load in case someone in that chain leaves…
19:01…and we've all been in projects where a key decision maker has left…
19:05…and if you haven't really been actively engaging other people on the city council, on a board…
19:13…the people who are your bosses and boss's bosses and keeping them involved…
19:19…and keeping on, particularly in this in financially stressed time, your project budget's going to go away.
19:25So, it's sometimes a really hard thing for project managers to embrace…
19:30…but it's a critical piece of kind of what you have to embrace as a project manager.
19:35And I think, don't…don't underestimate when…when, you know, one other key component of the sell mode is…
19:41…a lot of times a project leader or project manager in that role is…is also being the peacemaker.
19:49You can be going in and impacting an organization, changing the way they've been doing business for 30 years.
19:56And through this sell mode, it's…when Gerry says spin or PR, it's not false spin or false PR.
20:04It is an opportunity for you to get in front of all your customers and stakeholders.
20:08It's an opportunity for you to work with organizations that may be kind of going against each other on things…
20:16…and try to bridge the…bring them together, become that peacemaker, not to step away from it and say, well, that's their problem.
20:24I'm…I'm…I'm focusing on my project, because at the end of the day, you're delivering capabilities for a mission or a business need.
20:33You're not just completing out the system.
20:36If you deliver a system that nobody wants to use and work with, then…then what have you accomplished.
20:44Manage change. I guess it's probably hard for some of y'all to see this. It will happen; get over it.
20:52I mean, that's…that's just the reality.
20:56We have a tendency, guilty as charged, that at times I'd become very risk averse.
21:04You know, I want to set everything up and, by God, I've got the plan.
21:07I know…I know how this is going to happen.
21:09I…I know what we've got to do to make this work, you know, whatever the case may be.
21:13I've got my playbook.
21:15Somebody comes along and says well, hey, I want to change that up a little bit.
21:18Sometimes I reaction is, whoa, whoa, whoa, whoa, whoa, whoa, hold on.
21:22If I change this, how am I ever going to hit my target?
21:26But the reality is, going back to what Gerry was saying…
21:29…things have changed a lot from a financial standpoint, technology in general, what's going on in all of our business environments.
21:37And the reality is, you're going to get new requirements, and you want to…
21:41…you want to deal with those as they come up during your project plan.
21:45Now, I'm not talking about, you know, changing the color of something or some minor change within the application.
21:52You need to deal with those certainly.
21:54But what I'm talking about is, as your stakeholders become more aware of what the system capabilities…what they're going to offer…
22:03…they're going to begin to see other opportunities to enhance that business value that was originally targeted for that project.
22:11Better ways to improve productivity that maybe you never…never identified at the beginning of the project…
22:18…or that nobody really envisioned in the business case phase, but as the project progresses…
22:24…they're going to see that, oh, wait a minute.
22:26If we leverage this function, or if we can put a capability in that does X, we can even, you know…
22:31…as opposed to a 30 percent improvement, we can get a 35 percent improvement.
22:36You as the change agent, you as the one who's trying to deliver success into the organization…
22:41You need to be prepared to accept that and be prepared to deal with that.
22:46Now, that doesn't mean it's not going to cause impact.
22:49It doesn't mean, hey, thank you very much, we'll just do this and move on.
22:53You need to understand how it's going to impact your schedule.
22:56You need to understand how it's going to impact your project.
22:59But there's a couple tools or a couple ways to kind of deal with that.
23:03Obviously, if you have your business value identified early, back to slide 1, and you know why you're doing the project…
23:10…then as a change comes up or as an issue comes up, that's your ultimate arbitrator.
23:16That's when you look at that change and you say, okay…
23:18…how is this going to impact what we're really trying to accomplish within the organization?
23:23If it doesn't have an impact on business value, then that's a different conversation.
23:27If it's going to deliver more value into your organization, then it's probably something you want to consider.
23:33Using a phase-based approach also will…will…is a nice tool to have in your toolbox for dealing with that change.
23:41You may not be able to squeeze it into that immediate phase in front of you, but the fact that you've got another phase coming…
23:47…and another phase coming, allows you that flexibility to plan that change, to prepare for that change.
23:55And I guess that's the fundamental thing is understanding that changes can happen, be prepared to deal with it ahead of time…
24:02…build it into your planning for the project so it doesn't catch you by surprise and doesn't make you the no guy.
24:08You know, you don't want to be the guy that's constantly saying no.
24:11You want to be the guy that's…that…that can consider it and say yes or no based off a rational approach.
24:19And…and in an enterprise project, which is usually long, drawn out over multi years and have a lot of features and functions…
24:27…one of the first things you'll probably need to do early on in the project is really set up how do you manage change?
24:33What is…don't wait for it to happen.
24:35So in an enterprise project, you're usually going to have some sort of change control board.
24:39You're going to have some sort of workflow process to manage change.
24:43There's some really great…we've got some resource slides at the end here.
24:47On our esri.com site, there's a whole project management section…
24:50…in case you never knew that Esri did project management, we do.
24:54And there's some templates there for change control board stuff and a whole bunch of things.
24:58So there's a lot of things you can use out there and, again, the whole thing about change is it will happen…
25:04…plan for it and get over it.
25:06And…and capitalize on the things that are really great changes.
25:10Not every change is a negative change, but they all have that impact on those three constraints.
25:15It's going to change my schedule or my scope or my budget.
25:18And you need to be able to take advantage of how you balance those and to create off those.
25:25Yep. Question.
25:27[Audience question] I have a question about workforce and change and going back to your previous sell slide…
25:33…when you're implementing a change to a legacy system, modernizing a legacy system…
25:39…is it…have you found that it's better to, during the implementation phase…
25:44…include the smaller group focused explicitly on that…that project, or include everybody…
25:52…a semblance of everybody in your organization?
25:55Repeat the question?
25:56Oh, yeah. In dealing with…in dealing with a new system, replace…replacing an existing system…
26:03…where you're going to impact potential business process or workflow within our organization.
26:09Do we find it's…there's any lessons learned or best practices around that? Do we focus on a target area or a pilot area or workgroup?
26:19Or do…is it more of a big bang approach where maybe bring in multiple people across the entire organization?
26:27Both ways can work. I think my preference and what I'm most comfortable with is…
26:36…I like focusing on an initial target workgroup for validation of the workflow throughout the course of the project.
26:44So one of the things that I…I talked about was phases, and I probably should have mentioned this. I glossed over it.
26:52When we talk about doing phases, you know, one of the things I like to focus on in doing a phase or a spiral…
26:58…is I want to make sure that I plan out a particular workflow from start to end.
27:04So when I…So I bring in the actual workgroup.
27:07You have your software testers, but beyond that, we want to bring in the users to have them start using the system and…
27:14…getting familiar with the system.
27:16So, I think there's certain strategies that you can employ, such as validation environments and validation labs…
27:23…where it's not just about testing, but it's also about a gradual training opportunity.
27:28You can bring in key people from different organizations, but as you head into the implementation phase…
27:36…if it's a legacy system that's been around for awhile and if…and if you can afford to transition from a legacy system…
27:43…and begin to move your resources off a different legacy system with old workflows into a new system with change…
27:52…if you do that gradually, it allows you to learn and also allows you to develop your own internal users to become your champions…
28:00…for that next workgroup that's coming down the line.
28:03I guess I would have…a…a…a comment that it depends on the…how integrated and utilized the legacy system is.
28:10So if it's a legacy system that's in a…an agency or a city government that is in every tentacle of the organization…
28:20…there are…I think there are two things you need to do.
28:22One is, you need to have representative people who are going to be effective engaged early and often.
28:29And you make those some sort of steering committee and you get them involved.
28:33But we found that implementations that are so elaborate don't work from an implementation strategy.
28:42You really need to say, okay, in this big legacy system, I'm, you know, the first phase is the planning department…
28:50…or some part of the agency.
28:52And that's the focus group we're going to get on board and pilot.
28:57But you're at the same time on a parallel track engaging everyone else in that organization saying…
29:03…here's the big plan and how we are going to schedule it all out.
29:06So I think if it's something that is really impacting many, many places in your organization, you kind of have to do both…
29:13…and you do them at two different levels.
29:19Well, that was your opening act. _______________ [Inaudible/Unintelligible].
29:22So I'm miking up ________ [Inaudible/Unintelligible]. You are up.
29:24So I take the next five.
29:27So, any questions while we're just changing mikes here? Because we only…they only gave us one.
29:30You…you can tell we both have the same accent. So…so it should be an easy transition. Yeah.
29:35Yeah. I'm from Atlanta, too. Little further across the pond.
29:43Okay. By the way, I see a lot of people taking photographs. That's great.
29:47You are going to get all these slide decks. They're on the presentations materials that you get.
29:52So you do get all of these slide decks.
29:54So, the next five. Involve IT early and often.
30:00This is really critical in…in this technology time.
30:06GIS is not just a little special niche that's sitting in some department.
30:10It is a full-on stack Correct that slides into your IT space.
30:14And, you can't…most departments have a GIS specialty, but in an enterprise system…
30:21…you're engaging multiple agencies, multiple departments, and you need to engage IT.
30:30I can tell you from experience that if you do not engage IT early, you're project's not going to work…
30:35…because you'll find out as you go into testing and staging that some key critical things that you didn't know about…
30:43…the organization doesn't…and when the IT front says, no, we're not doing that.
30:47As much as I don't want to say this, I've actually gone down project requirements on…and built systems around a…
30:58…a Linux system to turn around to go into the IT to deploy and say, we don't do Linux.
31:05So you don't want to find that out when you're ready in staging.
31:08That's kind of an extreme, but…but there's lots of other examples of that as well.
31:15What we try and do early in bringing people together and…within an enterprise system is…
31:20…you must have some IT stakeholders at the table.
31:23Not just end users, not just the business sponsors, but someone from IT who is sitting there and nodding and understanding what GIS…
31:31…they've never heard of GIS.
31:33They've heard of Oracle and SQL Server, and they're comfortable with DBMSs…
31:37…but they don't know anything about GIS, and they just think, we just put it on this little box and it'll be fine.
31:42It's not going to work.
31:43It is such an integrated place in the platform of web servers and ports and all sorts of other things that I know nothing about…
31:50…that you've got to have them at the table.
31:53And you've got to recognize that they're going to say things that you probably don't want to hear.
31:58So, we actually worked on a project recently in the last couple of years where at the user requirements meeting…
32:06…when we were trying to do features and functions and what is it the business that they're trying to support…
32:11…one of the key things within this federal agency is they wanted to be able to engage in the Internet…
32:18…and bring data sources down in real time and download from all sorts of websites…
32:24…to get the best data that they could as quickly as possible.
32:28We then turn around to the IT people and say, what's your requirements in terms of the stack of things that we're allowed to do?
32:36And one of the first things they said, no outside Internet…Internet access. Period.
32:41And so all of a sudden you've got mutually exclusive requirements that the IT says, no outside access…
32:49…and the business is saying, we must have that.
32:52And so we were able to really negotiate early on that the IT people who were very stuck in their ways…
33:02…and following very focused agency specifics, had to be engaged and brought in early and said, you've got to change.
33:11And that…that process of doing that took a long time.
33:14If we had waited, we would never have got the project off the ground.
33:18So it's really critically important to identify an IT sponsor and have them at the table early, and get them engaged and trained.
33:28It's really critical.
33:30You cannot have someone who is the best DBA in the world manage your geospatial database…
33:36…because they will go in directly at the row level and start manipulating things and corrupt your database in a heartbeat.
33:42I've had it happen numerous times.
33:45You know, so the whole idea of training people in the IT space is getting them to SDE training, getting them into stuff.
33:54You know, they'll just want to assign a DBA and say they're done. And that's not going to work.
33:59Okay.
34:01Question. Oh, question, sorry.
34:02[Audience question] What if you have a client on the business side who doesn't want to involve the IT…
34:08…because of their rigid requirements?
34:11Then you've got a problem. How…I mean…the early…you know, one of my mantras in project management is…
34:19…the earlier you surface the problem, the quicker it's going to get solved.
34:22And one of my mantras to my boss is, he doesn't want to hear about problems…
34:28…when the only thing he can do about it is throw money and people at it.
34:31You know, if he finds it earlier, you got to bring him to the table.
34:36If the business client says, I don't want to deal with the IT, they're hard...
34:40…you've got to take it on.
34:41You've got to have separate meetings with them, bring them to some meetings.
34:45Why are they are hard? What are the issues?
34:48Because ultimately, it's, you know, ultimately you've got to put this system someplace.
34:55And from…and in changing times, it's not sitting in the planning department or the engineering department.
35:01It's sitting in IT infrastructure.
35:04And, they'll look at you and say, you can do whatever you want, and, but then as soon as you give them a set of requirements…
35:13…they say, well, you can't do that.
35:14And so you've got to get them engaged early.
35:17And I…I…I would seriously think about how is that project going to be successful if IT's not involved.
35:24Yeah, and I guess just to…to further emphasize that and, I mean, this is somewhat obvious…
35:30…but, if they're hard there's probably a reason they're being difficult.
35:36It's not just, yeah, well, most of the time it's not because they want to be.
35:40They are very risk averse. Yep.
35:42They are responsible for the security and a lot of assets within a given organization.
35:50So, while some of us in, you know, at times of, you know, made my comments under my breath about certain security procedures…
35:58…or whatever in an IT department…
36:00And CNAs in federal agencies.
36:03But there is a reason for it, and, you know, just getting at that underlying reason for it…
36:05…and, you know, just getting at that underlying reason for it…
36:09…and sometimes it…it…it just takes somebody in the business willing to cover them for making a change in procedure.
36:21So they have their playbook that says it's X, Y, and Z, and, hey, that's what they're going to do.
36:27They've been instructed. That's the way it is.
36:30If you got the right business champion associated with your project, sometimes you can get them to step up and say…
36:37…hey, I'll own this risk and have them champion that risk, if you will, and makes IT feel a little bit more comfortable…
36:45…because there may be…agreeing to it, but they're not the ones driving it…
36:50…so they can sometimes feel more comfortable about that change.
36:53I think there was a question. Yep.
36:55[Audience comment] I just had a comment about, at some point if you're attempting to avoid IT, at some point that confrontation...
37:05…it's going to happen, if either at the support level, at a time of upgrade level…
37:12…at an interface level if you decide you want to interface to another system…
37:16…at some point you're going to have to have…
37:18You have to bite that bullet and…
37:21[Audience comment] So the earlier the better is your point.
37:22The earlier the better, and…and that's a good mantra in any of the problems you're going to face.
37:27But it's really critical on the IT front, because things are changing so much…
37:31…and policies are changing that, quite frankly, a lot of the IT policy side is not keeping pace.
37:38So one of the things we try and do early in a project cycle within an enterprise project in one of the early phases…
37:44…I think Glenn mentioned it earlier was, in one of the early phases I call it connecting the dots.
37:50So, you know, if you're standing up a web viewer that's going to put points on a map for something…
37:58…and, early on, get IT involved, get a server set up, take the Flex or the Silverlight or whatever your…
38:10…your poison is of how you're…you're building this, get the free one that we have loaded on there…
38:15…and make sure you can connect to ArcGIS Online.
38:17That simple one, two, three step, we've done it numerous times in projects, and I can't tell you how many IT things we've uncovered.
38:25They won't open port 80.
38:26They…they won't let us do a reverse proxy.
38:30All the technical mumbo jumbo that's out there, you find that on the first three weeks of your project.
38:36It gives you…gives you 10, 12 weeks to fix it.
38:39You're not finding out when you're deploying at week 10, and next week your business manager's got the big demo.
38:47So the earlier the better. There was a question.
38:50[Audience question] Yeah, would you deal with it the same way like you have squadron-level IT, wing-level IT, base-level IT…
38:59…and DoD-level IT?
39:00Okay.
39:01[Audience question] It's hard to get them all in sync.
39:03Yeah. So the question or comment is, if you've kind of a very hierarchical IT structure, where do you engage?
39:09And, I guess my experience is that it depends what you're implementing.
39:13On an enterprise level, you're probably going to be impacting all of them…
39:17…so you're going to need this committee's of how they organize which is sometimes baffling to me, to be quite honest.
39:24But you're going to need to think, where does it fit in that hierarchy, and usually what I try and do is go one above it.
39:31You know, so, you know, particularly in a hierarchical military.
39:36If it comes from the top, it…it…it…it really helps to get it flowed down, so we…we usually try and engage at that level…
39:43…but, again, it depends on…on what you're implementing.
39:47There's a question at the back.
39:48[Inaudible audience question]
40:12Yeah, that's…that's…hmm…not a good PM strategy, but, you know, the comment was, you know, that…
40:21…IT is there to support the business, not the other way around.
40:24[Audience comment] Just so you know, IT supervisor…
40:28[Inaudible audience comment]
40:33I love this IT supervisor.
40:36Can you get duplicated into some of my agencies? I'll give the list to clients.
40:39[Audience comment] At the end of the day, we're __________ [Inaudible] value. That's a problem, and there can't be legitimate concerns, right, so _______ [Inaudible].
40:47Correct.
40:48[Audience comment] I can't offer it. If you get my manager tell me I can do it, we'll do it.
40:53Great. [Audience comment] Here's the risk. __________ [Inaudible] the risk, we'll get it done.
40:57And that's exactly the IT attitude you want.
40:59Unfortunately, when I work, I don't often get that.
41:02And so what we try and do is…is…is you've got to engage them early. You got to…
41:08Most IT people are…are bound by rules and regulations.
41:12You kind of have to figure out, you know, how to circumvent some of those and them changed.
41:18And then the case where we had mutually exclusive IT says, we can't do that and the business is saying we will…
41:25…we went, you know, to the…the boss of everyone and said, the business…
41:30…this is what it's getting to take to fill this business need.
41:33This is what we need to do, and IT won't do it, and they changed the…we got them to change the policy.
41:39But it was something that didn't happen overnight.
41:41It took a lot of meetings; it took a lot of negotiations; it took a lot of conversations to make sure that they weren't…
41:48…they didn't think we were doing something crazy, that there was a lot of things considered.
41:51So, earlier the better you get things, particularly on the IT front.
41:56Next one.
41:58Ah, okay.
41:59This is perhaps a sacrilegious slide to put up in a GIS Esri conference.
42:04But, you know, on Monday you saw some amazing demos.
42:08I mean, I sat in the audience, too, and I'm like, really, we do that, and just some breathtaking ideas.
42:14But don't get enamored by Monday.
42:17The reality is, you know, you can get a vision from Monday and some ideas, but a lot of the…
42:23…some of the things you saw Monday may not be practical for your business.
42:27So, one of the things that always happens after user conferences, I have lots of clients who come up and say…
42:33…that mobile app that Bernie Szukalski showed on stage on Monday. We want it.
42:39And I say, why?
42:42What business function, you know, if…if…if you don't do any mobile activities, why?
42:47Now there may be some very valid reasons and, you know, we've implemented some things that are very strategic…
42:55…and targeted that have nothing to do with the business because perhaps we're buying credibility with upper management.
43:04And that's a really good strategy to have.
43:06So an example of that is, if your…if your upper management are all iPhone and smartphone enabled…
43:14…then maybe even though the business doesn't need it, maybe doing some dashboard on an iPhone…
43:20…or publishing some web services that they consume would be a really good idea to get them to buy in and engage on the technology.
43:27But the…the bottom line is, if you need a truck, get a truck. Don't use a car.
43:32So, you know, the whole idea of writing your technology to your business is just as critical…
43:40…as writing your project management strategy and your communication strategy...
43:45…which is sacrilegious with…you're going to see loads of shiny objects.
43:49If you go down to the main floor and go on the vendors, this…and on the Esri side, there are some really amazing things…
43:56…but, back to that first slide…what is the business reason you are implementing it?
44:00And it's not the technology.
44:02The technology is the solution, not the business problem. Okay?
44:11[Audience comment] Do you like the car?
44:13Yeah, that is Glenn's car by the way.
44:17Okay. This…we've been petitioning to have a sessions on requirement gathering for a long time.
44:25To me, we could do a whole tech workshop for a whole day on how to do requirements gathering…
44:30…and there is a 20-minute one that's going to happen on the demo floor.
44:33We're doing it twice, one right after this session at 10:00, and then there's one later this afternoon that I'll give.
44:39But requirements, requirements, requirements.
44:42As Glenn said earlier, we get pulled into some really ugly projects that are heading south badly.
44:48And the two things we ask for usually when we go in is, let me look at the project planning schedule…
44:53…let me look at your requirements documents.
44:55And we go off in the corner and we usually bang our heads on the table.
44:59Because I can tell you right from the very beginning by looking at the requirements documentation and…
45:05...by the way, a long Excel spreadsheet line by line is not a requirements documentation, in case you thought that was the case.
45:13It…it is such a critical part of every piece, particularly in an enterprise project that is complex and long.
45:19So, we're not going to spend the rest of the session on requirements gathering…
45:23…but there's some fundamentals that you should take away from it is, and there are some amazing books…
45:28…we've got some references for some books that are good, but any good requirements project management class that you can take…
45:36…whatever the methodology they take, it is an art; it's not a science.
45:41But there are some good practices, and they should really be about what are you building.
45:47They should be…they should be in the language of the users.
45:51As I said, a long Excel spreadsheet that we respond to all the time on RFPs…
45:55…when they put in an appendix of 500 things it should do is not a requirements document.
46:01That's the…perhaps might be the first phase.
46:06But they provide traceability.
46:07If you don't know what you're building, how do you know you're successful?
46:11How do you know when you're going to stop?
46:12How are you going to put things into phases?
46:15So the requirements process and the documentation you do with that is absolutely in…the most…
46:23…I'd say even over project schedule, the most important thing that you need to do.
46:26And it can be as easy on a smaller project as Excel spreadsheets and a Word document that translates those into workflow.
46:37The key is workflow.
46:40So, if you're building a system for a map viewer that the public's going to be using…
46:45…what is the two things you want them to do, and write them out.
46:50And…and then from that, there is a really easy way to start saying, okay, from that, what's the data I need to support that?
46:57What should you be focusing on?
47:00And there's lots of different strategies.
47:02We can go on and on about requirements and don't get me started.
47:06But there's lots we can talk about on that and we can certainly do that afterwards.
47:09Can you show the next slide?
47:10And, just before moving to the next slide, I guess, describe the whatnot, the how, in the requirements…
47:20…one of the things that…that I'll look at when I'm looking at a requirements volume is…
47:26…if I start seeing a requirements document that's describing how to zoom or how to pan or how to do some of those things…
47:35I…I immediately become concerned, because those are things that I think we've, over time, we've all become familiar with.
47:42We understand how they work in the underlying COTS technology…
47:46…and what we really want to see in those requirements is what are you trying to accomplish.
47:52What…what is that workflow? Business workflow.
47:53What is that scenario?
47:57Now, there're are going to be certain things that isn't satisfied by the COTS technology.
48:02It is very mission specific or business specific, but describing it from the standpoint of a user…
48:09…you can have a list of 500 capabilities, system capabilities, and you could actually complete all 500 capabilities…
48:17…but if there's no thought put into how those capabilities are orchestrated together, of how it comes together…
48:24…how does somebody execute a function or proceed through a scenario…
48:30…you can check the box for all 500 but deliver no business value.
48:35So, seeing that relationship between the two and understanding what the business value is, what the workflow is…
48:41…and what are the system capabilities to support that is extremely critical.
48:49So this is an attempt to try and bring again some fundamentals on requirements gathering.
48:55So in the top part, it's a line item on a spreadsheet, but you've translated that into…there's many ways to do it.
49:03It's in more user specific…
49:04…and then there's some…some potential things that you as an enterprise system would need to build.
49:11So, you need workflow. You need use cases. You need a domain model. You need a design model.
49:17And on an enterprise, you need all of those things.
49:19On…on a smaller project, you can do this in two hours.
49:24You know, clearly an enterprise system, it's much more involved.
49:27There's a lot of people involved.
49:29But there's really good software and tools out there…Enterprise Architect Team Foundation Server.
49:35There's a whole bunch that we use on really, really big projects where you really need to assign IDs and track traceability.
49:42But fundamentally, a lot of these documents are what you should be using.
49:47There's a lot of really great literature that you can buy on Amazon and all sorts of places.
49:52Any good solid requirements gathering process is…is important, and it's…it's also important to understand…
50:00…and we've been in cases when you gather requirements that are going to be mutually exclusive.
50:04And that's the whole part of an enterprise system is…is…is involving early, creating a vision, collecting requirements…
50:11…shuffling them into phases, and then packaging them for delivery.
50:17And it might mean that where you end up, at the end of the year is very different where you thought you were going to be…
50:22…because of change and shifts in requirements.
50:26But the only way you're really going to know what you're supposed to be building is if these sets of documents are in place.
50:33And without them, so, when we get called into ugly situations and we ask and they don't have them…
50:39…or all they've got is the first thing, which is an Excel spreadsheet of a list of 500 requirements, it's painful.
50:46Because the end users don't know what they're supposed to be getting.
50:50The workflow that one end user in region 9 supports versus another end user in region 2 supports, might be very different…
50:59…and you need to kind of figure out, are we doing both, are we modeling both, is one more important than the other?
51:05And these cases are…are the critical way to translate those.
51:09And there's…there's templates up on our website about a use case and what a use case is.
51:14So we can certainly go ad nauseam and talk about that.
51:18But that…that…that 20-minute workshop might give you some good ideas as well.
51:24Okay. Even in an enterprise system, in…in today's frantic world when you're trying to get things stood up…
51:35…you really must sit back and start to say, what can COTS give me first?
51:40It's…and by COTS, I don't mean just Esri software.
51:44I mean the RDBMS you're using or some extension that a business partner puts together…
51:50…or, you know, if you're in the utility business or you're in the planning business…
51:54…there's loads of business partners who have very focused applications that they've written and, you know…
52:00…there's not the money these days to write custom systems, there's just not.
52:04So in the…even in an enterprise system when you're perhaps going out and…and creating new editing tools…
52:11…there are great templates, there's great packages out there that do a lot of that.
52:16You really must look at what does COTS give me first?
52:20And that should be your approach.
52:22And we often in our phasing, one of the things we do, even if we are building somewhat of a custom system…
52:28…we'll stand up the COTS editing environment first if we're doing an editing.
52:32If we're building a web viewer, we'll…we'll take the COTS one, we'll connect the dots, load some data in…
52:39…and get people buying into the concept of viewing their data on the web.
52:43Sometimes they've never seen their data on the web, and they don't need to wait a year to see it.
52:47You can start publishing that right away.
52:49So it's, again, figuring out in the COTS what…what value does it bring, and how do we implement that…
52:57…and…and our strategy usually is get it in the early phases.
53:01Don't wait to, in nine months down the road trying to show them what COTS does.
53:07And you need to make some hard business decisions.
53:09Again, that…that three constraints of scope, schedule, and budget, you know, if…are they in parallel?
53:18If…if…if there's an editing environment or one of our free viewers, if that does 80 percent of what you want…
53:28…you need to kind of consider, is it worth spending a million for the other 20 percent?
53:32And in this environment, you've really got to start thinking about those things and…and…
53:35…what is the priorities that give me the best value right now in my phasing?
53:40So, we really look to try and leverage that.
53:45That doesn't mean that you can't configure and completely change things.
53:50I mean, we've got examples of…of people's sites who've used the base web viewer or the editing environment…
53:55…and you wouldn't recognize them because you've configured them with different workflows, you know…
54:00…a lot of the data flow manager and some of the other tools that really help you in workflow.
54:05I sometimes don't recognize that they're the same base tools that were configured differently.
54:10So sometimes that's a really great place to start, and we always look at it from an enterprise system as the first place to start.
54:24Implementation in an enterprise is a continuous process.
54:27Even though your schedule might say 18 months, you've got to remember that things change and things evolve…
54:34…and move forward and you've always got to be going back to those early visionary documents that you write…
54:40…and touching base and making sure that you're on point.
54:44And what we really like to look at is, even in the implementation process, you've usually got multiple spirals…
54:51…you've got different teams spun up, some doing testing, some going back and saying, did we get the requirements right…
54:56…some code development.
54:59But you've really got to start looking at how we deploying and moving that forward through that cycle.
55:05We call these spirals because there isn't an end.
55:09Once you've deployed the first phase and you've implemented it and got it out there, you're…
55:14…you're already got a team geared up to think about the next phase.
55:18And the critical things to think about in that are training and who's maintaining it and who's using it and how are you monitoring that…
55:26…so there's really great tools out there and available now to look at, are people using the system?
55:33Have you built a system that no one is using?
55:35Have you built a website that no one's going to? Why?
55:39And…and really going back and…and trying to retrofit and, in the next phase, what you've learned.
55:47So it's really important to think about things as a cycle and be realistic about what you can get done.
55:54And I think the second bullet on here I think is key, job or mission-specific training.
56:01A lot of times, we have a tendency to focus on, once again, feature, functionality, capability…
56:06and…and that's where the training focuses as well, showing the tool, showing the capability.
56:14But we sometimes fall short in showing how is it going to be used within the context of executing a day-to-day workflow…
56:20…or a job or what…how are you actually going to use this to accomplish what you've been doing for 20 or 30 years…
56:26…as a particular user or a person within…within an organization.
56:30So it's…it's not just the capability but job or mission-specific training.
56:37Two minutes and then we'll do questions.
56:39Okay. Is that the last one? It is.
56:46So, we like to give, beginning and end, give you right up front what you got the 10.
56:50We try to talk through them.
56:51Again, they're not in any priority, and I think some of them are emphasized more…
56:55…just because if we've come out from a project that is requirements challenged, shall we say, we emphasize requirements.
57:03But our…our idea is that all of these are important as a project manager…
57:08…and I think more and more project managers are having to embrace technology.
57:14They're having to wear an awful lot of hats.
57:16You can't just go off in a corner and…and put your head down and get into Microsoft Project and not talk to people.
57:23You know, so communication, even though it's not up here, we used to have a communicate, communicate, communicate one.
57:30But it's in…it's…it's in all of these and how you communicate about your enterprise strategy and planning is really critical.
57:40You know, how you roam the corridors and walk with your…talk with your programmers and find out what's going on…
57:46…that's when you really find out what's going on.
57:48Not at the status meeting that you hold every morning at 9:00 in the morning.
57:52No, it's when you find that they're working late at night and they've got a problem going on.
57:57So, even though communication's not up there as a specific one, it's really implied through a lot of these.
58:05We've got about 10 minutes or so for open questions and free consulting.
58:12Hey, it doesn't happen very often with Esri, so come on. Yes.
58:17[Audience question] Can you say some words about data migration?
58:19Okay. Question is about data migration. Do you want to take that?
58:25Yeah.
58:26Oh, before everyone starts to leave, the evaluations are online.
58:29Please go do them, because we really would like to hear from you about what's missing.
58:33What are sessions that you would really like to hear?
58:35If you're in the project management field, we really would like you to tell us about that because they do influence.
58:43We'll get your question in a minute.
58:44[Audience question] Would you put that last slide back up?
58:45Put the last slide back up.
58:49So the question was about data migration. We don't in this session focus specifically on that.
58:56Obviously, that's critical to any project that involves geospatial data, preparing that data.
59:05Once again, I like to…I like to approach data migration similar to feature functionality…
59:11…that in the context of proceeding through the project, I don't wait till the end to do data migration…
59:19…or migrating data throughout the project.
59:21It is part and parcel to what I like to call the validation lab or…or when you're getting your users to start working with the system.
59:32Part of that should also be refining and truing up your data migration process.
59:38And then, one…one thing that can be particularly challenged, especially in a large enterprise…
59:43…with a lot of disparate geospatial data is, you know, not choosing the…the best data that you know exists within your organization.
59:54I mean, it may be good to start on that just so you can get some functionality out there…
1:00:00…but I think all of us are aware that, you know, there may be one region or one group within a given organization that you realize…
1:00:08…hey, their data's maybe not the best, maybe they haven't been extracting it…
1:00:13…or maintaining it to the standards that we want from an organizational standpoint.
1:00:19Don't forget about those. Don't put those off to the end.
1:00:21So try to get a good sampling of data across a particular organization or a region.
1:00:27But…but to do it early. Just like everything else. Don't wait till the end, hit a couple of areas through your process…
1:00:33…make sure you're going through that, because that's going to help you evolve your migration process…
1:00:38…along with what is it going to mean to do system deployment, because they need to be close, obviously, closely coordinated.
1:00:45And particularly if the data that you're using has never been seen in the GIS before, red flag it.
1:00:51Because don't…don't delay in understanding what that quality is because more than likely, it's not great.
1:01:01And we've had loads of examples, and I will not name the company…
1:01:04…but they gave us their data file that we were going to put up on the web, and let's just say…
1:01:12…it was a large retail company that sold a product of some sort that you consume every day in your car…
1:01:18…and we call it petrol in Europe, but it's not here, called that here.
1:01:22And they gave us their data file, and we were going to be loading up.
1:01:26We loaded up. We made these beautiful maps. We put it on the web. We sent it to them…
1:01:30…and within 10 minutes of them getting this, they said it's wrong, completely wrong.
1:01:34The data that they had stored, all the time thinking it was the address of the petrol stations, was the address of the owners…
1:01:42…and they'd never seen it on a map before until you put it on a map.
1:01:46So, you know, on the data legacy side of things, you know, these got these massive data warehouses and tables of things…
1:01:53…but they've never seen them on maps before, and, you know, the GIS and maps shows warts…
1:01:59…and they're really ugly warts sometimes.
1:02:01So it's really important to kind of figure that out early.
1:02:05[Audience question] _____________[Inaudible] you had templates _____________ [Inaudible] web site or product management or…
1:02:09Yeah, there's…there's a bunch of templates up on the, I think, support.esri.com, then there's a project management link.
1:02:14If you can't find it, just let us know.
1:02:16And then if you head down to the Professional Services island, they can show you a whole bunch of templates.
1:02:20Yep. Guy in red at the back. Did you have a quest…? Sorry, lady.
1:02:25[Audience question] [Inaudible]
1:02:36I…I…I would…the comment was that implementation that is not a continuous _________________[Inaudible]...
1:02:41…and I would challenge that in this environment that it's…that…that you're never ending.
1:02:46There…there certainly needs to be boundaries drawn and know when you're complete…
1:02:51…but it is an evolving process that changes an awful lot, and we're seeing it being very, very much continuous.
1:02:58Comment back here.
1:02:59[Audience question] [Inaudible]
1:03:12Yes. Actually, there's a tech workshop that's going to be listed on the…if you don't have one of them…
1:03:17…it's how to build a good project plan, and it shows…it takes you through the steps…when is it? 2:00 this afternoon.
1:03:23Is it on that list? Let me see.
1:03:27Creating a manageable project plan. It's at 10:30 in the Professional Services island…
1:03:31…and then we’re doing it again. I'm doing it at 1:30, and it'll give you ideas of how to break things down…
1:03:37…and tools to use. Okay.
1:03:39[Audience question] Do you have another copy?
1:03:40Yep. This ________[Inaudible]...Is that yours? We've got some more copies here.
1:03:43__________[Inaudible] orange?
1:03:45[Audience question] No, I was just wondering ______________ [Inaudible]
1:03:49[Audience question] Can we have a copy of the ______________ [Inaudible]?
1:03:51Yeah, you…everyone gets it. There's a…you get every presentation that's shown on the tech workshops.
1:03:59[Inaudible audience question]
1:04:00It's…a link is mailed to you as part of your registration after the conference. There was another question?
1:04:14[Audience question] Number nine. Number nine.
1:04:15[Inaudible audience question]
1:04:17Yep.
1:04:18[Inaudible audience question]
1:04:34So, the…the…
1:04:35[Inaudible audience question]
1:04:37Yes, so the comment is…is number nine, which is use COTS as much as possible…
1:04:42…in conflict with that you have to build a lot of custom stuff in GIS needs to be custom…
1:04:46I…I…I think that was certainly true years ago.
1:04:50I think more and more, there are solutions and templates and things that you should leverage first…
1:04:56…resources within your agency and time and budget are scarce.
1:05:00So you need to be plagiarizing whatever you can get your hands on from Esri or from a business partner…
1:05:05…and configuring it first to meet your needs.
1:05:09So one of the things we run into all the time is, we've done editing in our planning department this way always…
1:05:16…and we don't want to change it.
1:05:18And I give them a proposal that says it's a million dollars to make that…
1:05:21…or, you can implement it for a hundred thousand dollars by taking their editing templates and changing how you do…
1:05:28…and probably improve your business.
1:05:30The workflow that you are following for editing for the first part was probably because Jimmy didn't talk to Mary across the floor…
1:05:38…and they were passing paper around to each other.
1:05:41So, you know, you don't want GIS just to implement a system that's bad anyway.
1:05:46That's just going to be a bad GIS system. Sir.
1:05:50[Inaudible audience question]
1:06:17Yep. I…I…we don't mean to say that you shouldn't be building custom. It should be the first place to look.
1:06:23There's a lot of systems you probably do need to build from scratch, but in today's resources…
1:06:27…you need to be really critical about that. There was a comment right there?
1:06:31[Audience question] Related to the requirements, do you have strategies for dealing with…
1:06:34…I don't really know what I'm _________________[Inaudible].
1:06:38Oh, yes. Yes. The idealistic clients. It's a bit like finding, you know, a husband or a girlfriend or whatever you're looking for.
1:06:47I know, but I'll know when I see it.
1:06:50prototyping. So the comments…
1:06:52…I mean, protyping's a good strategy for that, obviously. And that's why, I mean…
1:06:58…there's a couple different reasons why we go about a COTS-first approach.
1:07:02One of those is to put something in place as quickly as possible.
1:07:07A…a lot of people can get verbose in writing requirements and here's what I think it is, and blah, blah, blah, blah, blah…
1:07:14…but being able to prototype and show them something and say, Okay, well how do you want to tweak this…
1:07:19…or how do you want to change that.
1:07:21Even if you're going to customize it, just having something you can demonstrate and base from…
1:07:26…that's…that sometimes can help in that scenario.
1:07:28So…so demo…there's a tremendous amount of videos and demos on the Esri site.
1:07:32If you haven't checked out support.esri.com or some of the other places in there, there's an awful lot of things you can use…
1:07:38…as particularly coming off Monday's plenary. Almost all the slides will be up there and demos and videos.
1:07:46So one of things, you know, we do is, if…if you're building, let's just be simple…
1:07:51…if you're building a viewer again to show data on the web, you know, go to sites that do similar things.
1:07:59So if you're a city and you're… go to other cities that show how they're doing their parcel data.
1:08:04What are the…show them five different sites. What did you like? What did you dislike?
1:08:11Ask them what sites they like, you know, what's the look and feel, how user intuitive is it.
1:08:16Who are the end users?
1:08:18So we…there's a whole bunch of workshops and stuff we can kind of give you some guidance on.
1:08:22So there's a bunch of different resources that we've got up here.
1:08:25Some of them are just straight process type documents.
1:08:30We tend to follow a lot of the iconics process on the Rosenberg stuff which is very use case.
1:08:35It's…there is actually a GIS section in one of his books.
1:08:38He…he worked with our development team on…on how would you implement a GIS using iconics.
1:08:44So that's the kind of process we generally use on large systems, but there's a…there's a lot out there that you can leverage.
1:08:51This is the evaluation link. I don't know how it's going to go. We usually we hand out evaluations.
1:08:55But we'd appreciate feedback on content and presentation and what's missing.
1:08:59What would you like to see in a project management session, what resonated here, what didn't resonate…
1:09:07…and I think we're out of time, but I really appreciate you coming this morning. Thank you very much.
1:09:12Thank you.
What You Need to Know About Managing an Enterprise GIS Project
Glenn Berger and Gerry Clancy share best practices for managing enterprise GIS projects.
- Recorded: Jul 13th, 2011
- Runtime: 1:09:16
- Views: 79256
- Published: Sep 21st, 2011
- Night Mode (Off)Automatically dim the web site while the video is playing. A few seconds after you start watching the video and stop moving your mouse, your screen will dim. You can auto save this option if you login.
- HTML5 Video (Off) Play videos using HTML5 Video instead of flash. A modern web browser is required to view videos using HTML5.
Right-click on these links to download and save this video.
- 480x270:WebM (123.9 MB)MP4 (57.9 MB)
- 960x540:WebM (327.4 MB)MP4 (93.7 MB)
If you don't have an Esri Global Login ID, please register here.